no responses
January 9, 2026
30-Year-Old Stringerless Raised Floor Upgraded for Modern Rolling Loads and AI (20,000 SF, Zero Outages) Client 6, an insurance company, was operating a raised access floor (RAF) system more than 30 years old—and critically, it was a stringerless design. While stringerless floors can function in lighter-duty environments, they often struggle
no responses
January 9, 2026
Stabilizing Electrical Gear on a Deflecting Raised Access Floor (Zero Downtime) In Project 5, the facility’s electrical gear was installed on an older raised access floor (RAF) that was beginning to deflect under load. That deflection created a real risk to electrical stability and operational continuity—especially in a mission-critical environment
no responses
January 9, 2026
Corrosion Recovery and Full Raised Access Floor Replacement For Client 4, facility staff reported visible rust and corrosion on pedestals, stringers, and the underside of raised access floor (RAF) panels—a clear indicator that the subfloor environment had been exposed to sustained moisture. Our assessment confirmed the root cause: the site
no responses
January 9, 2026
Zinc Whisker Mitigation and Full Raised Access Floor Replacement (3,000 SF in <4 Weeks) Client 3 faced one of the most disruptive contamination risks in legacy raised-floor environments: zinc whiskers. It’s often debated because only a small percentage of facilities are impacted—but when it happens in your site, it becomes
no responses
January 9, 2026
Raised Floor Height Upgrade for Airflow Recovery (9” to 18”, ADA-Compliant, Zero Outages) Client 2 presented a classic but high-impact cooling constraint: a 9-inch finished floor height (FFH) that was starving the IT equipment of underfloor supply air. With modern heat densities, that limited plenum height made it difficult for the room to
no responses
May 6, 2025
Raised Access Floor Replacement Integrated into a Full M&E Data Center Refresh (3,000 SF, <2 Weeks, Zero Outages) For Client 1, the customer was executing a complete mechanical and electrical (M&E) refresh in their data center and made the strategic decision to include a raised access floor (RAF) replacement as part of the overall modernization